Bulk Storage Hardstand Construction
Terazzo Concrete Construction delivered all aspects of a Bulk Storage Hardstand Construction in Pinkenba, Brisbane.
Client: Bulk Sotrage Facility
Location: Pinkenba, QLD
Scope: ~3,500 m² heavy-duty concrete hardstand
Program: September–November 2025
Specification: 200 mm thick pavement slabs — full service: formwork, supply, place and finish
About the Project
The works comprised formwork, supply, placement, finishing and curing of 200 mm concrete pavement slabs across approximately 3,500 m², ready for frequent heavy-vehicle loading and yard operations.
Challenges We Managed
• Live site logistics: Continuous heavy-vehicle movements required careful sequencing to keep the yard operating safely during construction.
• Tight delivery window: The works were programmed between September to November, with limited scope for weather and supply variations.
• Drainage and levels: Precise falls were essential to ensure proper drainage and to avoid ponding across a large slab footprint.
• Quality controls at scale: Consistent finish and performance across multiple pours and pour breaks.
How Terazzo Solved It
• Staged construction management: We developed a pour plan that maintained access routes, with clear exclusion zones and a live traffic management plan to keep operations moving safely.
• Supply coordination: Batch timings and truck cycles were scheduled to suit the pour sequence, reducing wait times and keeping finishing on pace.
• Level control & drainage: String-line/laser level control, systematic screeding and diligent edge checks ensured specified falls and uniform slab thickness.
• Curing & early-age protection: Membrane curing and controlled stages were executed to manage shrinkage and support long-term durability.
Outcome
• Fit-for-purpose hardstand pavement: A durable, low-maintenance hardstand ready for bulk storage and heavy-vehicle traffic.
• On-time delivery: Works completed within the programmed window, despite live-site constraints.
• Safe and efficient build: Zero recordable incidents, with clear segregation of work zones and ongoing access for yard operations